Tower A, B & C: External Painting Status

Tower C: Badminton Court External Plastering completed

Tower C: Club External Glazing under progress

Tower C: Window/Sliding door fixing under progress

Pergola towards Central Courtyard are under progress

Swimming Pool –Tiling works completed, enclosure works to start shortly.

Tower B: Lift Installation under progress

Tower C: Sky lounge Glass glazing installation under process

Tower G: Light Mast structure under progress

Tower G: Entrance Lobby Status

Tower F: Entrance Lobby Status

Tower D: Party Hall Interiors work under progress

Play courts under progress

Path way to Swimming Pool

Outdoor Gym installation under progress

Few Photos of Apartment handovers in August 2018

Few Photos of Apartment handovers in August 2018

Few Photos of Apartment handovers in August 2018

Brigade logo
Live chat
Speak to Us
Please select your country and enter your phone number
Please enter a valid phone number
*We respect your privacy. Your Information is safe with us.
Connecting now...
Connection Established.
Please verify your number using the code below.
11001
Number verification successful
Number verification failed.
Call in progress.
Call Completed Successfully.
Call ended.
Our Agents are currently offline.
We've received your contact number and we'll get back to you shortly.
Oops! Something went wrong.
00:00:00